Re: Statutory Inspection planning in PM

$
0
0

Hi Dennis,

 

You can try the following process. It might help,

 

 

1: Assign an Order to inspection type 14 in configuration.

2: Create Master Inspection Characteristics (Quantitative or Qualitative as per your requirement)  and assign sampling procedure.

3: Create a task list with inspection point 300 and assign Master Inspection Characteristics to it. Assign control key PM01 (for internal) or PM03 (for external processing)

4: Create a Maintenance Plan with the same task list for an Equipment with the order type with inspection type 14

5: An Order will be created as per the schedule given in Maintenance Plan.

6: An inspection lot will be generated once the order is released.

7: Do result recording and usage decision for the same.

8: I think there is a provision to print certificate as well (I have not used it though)

 

Thanks and Regards,

Sanjay