STPR in MRP

$
0
0

Hi  Gurus  ,

 

I  have one requirement related to storage to storage location stock transfer  through MRP within the same  plant  .

As per SAP r/3 standard  I have created  one MRP area  & maintained the receiving storage location  in it  .  While maintaining  the material master I have also maintained the material in MRP area as well with  MRP type "VB" . System is generating the  STPR perfectly when stock falls below the reorder  level  .

My question is that can we transfer  the requirement from plant to MRP area ,  so that planning  in MRP area should not  be based on  reorder level  should done  be based on the  actual requirement .

As per requirement  from user , requirement  should be pass directly  from plant  to  MRP area so that  we can avoid using the reorder point & system to generate the STPR based on actual requirement  .

 

Thanks ,